I have created a copy of the Scrum process for my DevOps project, and created specific work item types (based on the task) for my two project teams(Design and Build). I would like to tailor their specific Sprint taskboards to display only the work item type relevant for their team, which I hope would in turn allow me to tailor the required columns to only those relevant for their work item type. Can you please advise if this is possible ?
0
votes
1 Answers
0
votes
We can customize the backlogs in the Process of the Organization Settings, and add the required work item types to the corresponding backlog level, but this applies to all teams, I am afraid that the work item type only displayed for a separate team is currently not supported.
We can remove states from columns in Column Options:
Update:
For example: If we want to remove the test2
column shown in the figure above, we need to map the state to test2
in the other columns: