0
votes

What I want to accomplish is an overview of PBIs that are not marked as done, but all the tasks of them are done (so that the PBI should be marked as done as well).

This is similar to this item: Query VSTS for all PBI's with no open tasks, except the answer is incorrect (because it does not check if all items are done, it only returns the items that are done).

screenshot of query This does return all PBIs who's tasks are marked done, but also PBIs that don't have tasks and only a parent.

Is it even possible to make such a query?

Thanks in advance.

1
Hi friend, any update for the issue? Can Shamrai's answer helps to resolve this issue? If the issue persists, feel free to let us know. See this, it just a reminder :)LoLance
@LanceLi-MSFT I let it be and just use it as I had it in my question. I marked his answer as acceptedSHEePYTaGGeRNeP

1 Answers

0
votes

No, work item queries do not support that. I think, that work maybe done with Power BI Reports: Connect to Analytics with Power BI Data Connector