I have a portfolio set up for my Project in Jira. It contains 6 or 8 epics and there are varying numbers of Jira tasks associated to each epic.
The Portoflio Scope view shows the epics and the tasks under each epic but the progress bar displayed for each epic or it's linked tasks does not show progress, even for epics where 90% of the tasks are marked resolved or closed.
All tasks have Original Estimates, Remaining time and those that are resolved, fixed have time logged against them.
I cannot find anything useful int the Jira Docs for tracking progress. I presume this is down to some smal config option or some feature of the epics or tasks but I cannot for the life of me work out what it might be.
We are using the cloud version of Jira.
Any ideas?