I have two project setup, both using the Scrum template. In one of them the sprint backlog board shows swim lanes/columns as I would expect:
- To Do
- In Progress
- Done
In my other project (the one that matters, of course), it looks as if the columns from the Backlog Items have been merged with those of the Sprint Backlog items and displays with all of these columns:
- To Do
- New
- Approved
- In Progress
- Committed
- Done
The extra columns appear to be read-only in the board view and do nothing but make the board cumbersome to use. Have I changed a setting somewhere that affects this?