We started using TFS 2012 recently for SCRUM methodology and below is our current structure. We have issue with showing the sprint cycles in the Product Backlog page:

>     Team Project 1
>       |_Iteration 1
>          |_   Sprint 1 of Iteration 1 (Start Date: 04/7/2014 End Date: 04/25/2014) 
>       |_Iteration 2
>          |_   Sprint 1 of Iteration 2 (Start Date: 04/7/2014 End Date: 04/11/2014) 
>          |_   Sprint 2 of Iteration 2 (Start Date: 04/14/2014 End Date: 04/18/2014) 
>          |_   Sprint 3 of Iteration 2 (Start Date: 04/21/2014 End Date: 04/25/2014) 
>          |_   Sprint 4 of Iteration 2 (Start Date: 04/28/2014 End Date: 05/2/2014) 
>           
>           
>     When I look at the Product Backlog Page, this is what I see:
>     Current
>       |_  Sprint 1 of Iteration 1 (Start Date: 04/7/2014 End Date: 04/25/2014)    
>     Future
>       |_  Sprint 1 of Iteration 2 (Start Date: 04/7/2014 End Date: 04/11/2014) 
>       |_  Sprint 2 of Iteration 2 (Start Date: 04/14/2014 End Date: 04/18/2014) 
>       |_  Sprint 3 of Iteration 2 (Start Date: 04/21/2014 End Date: 04/25/2014) 
>       |_  Sprint 4 of Iteration 2 (Start Date: 04/28/2014 End Date: 05/2/2014)

The configuration shown in the backlog page is incorrect, because the "Sprint 1 of Iteration 2" is the past completed sprint which is showing in the future, while "Sprint 2 of Iteration 2" is the current sprint which is showing under the future. Is there any configuration change that needs to be made in TFS 2012?

1

1 Answers

0
votes

Your iteration dates are problematic. Iterations aren't parallel processed timeboxes. You should think them as upper sprints.

So in your example sprint 1 of iteration 1 and 2 seem to be starting on the same date whereas such a thing can't be happening. You can't jump to iteration 2 before completing iteration 1. I think you are using the iterations as project branches, am I right?